The FAI and Production Readiness Kit HandbookChapter 20 of 22

Quick reference

One page to pin where launches are planned.

WhenDoWith
An order for a new part arrivesScreen triggers; list the order's first article clauses; enter it on the FAI plan logD07
Any change to a part in productionAsk the first article question; set the partial scopeD07, D11, E13
The drawing is balloonedOne line per balloon in the inspection plan; gauge check on every lineE11
Key characteristics are knownValues from the first part; control and reaction plan at the operationD16, E07
The traveler is writtenReview before release against drawing, order and plansE09
New fixture, tool or programValidation record before it makes product for releaseE10
One to two weeks before the first articleReadiness review; Go, Go with conditions or No goD09
Every setupSetup checks, every characteristic measured, release on evidenceE12
First article dayProduction route; balloon order; values; NCR anything outD19
Before the signatureCount, then check every section; reviewer is not the inspectorD08
After approvalKC data and capability; first piece every setup; triggers watchedD16, E06, E12

Five rules we never bend

  1. The first article is made on the production process.
  2. Every characteristic is planned before the part is made, one line per balloon.
  3. No first article on a process rated Not ready.
  4. A first article with an open nonconformance is not complete.
  5. The person who measured the part does not review the package.

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.