The FAI and Production Readiness Kit HandbookChapter 7 of 22

Inspection planning and key characteristics (E11, D16, E07)

With the drawing ballooned, the inspection plan (E11) gets one line per balloon: the requirement as the drawing states it, the class of characteristic, the operation that produces it, where it is verified, the method and gauge, the gauge's resolution against the tolerance band, the frequency, what is recorded, and what happens when a part is out. Its Plan check column stays crimson until the line is fully planned, and its Summary counts lines against the balloon count on the plan header.

Choosing gauges

We start with a gauge whose resolution is no more than a tenth of the tolerance band, and the worksheet checks it on every line. Resolution is necessary, not sufficient: a gauge that checks a key characteristic also needs a measurement study (E04) before its readings are trusted. Every gauge on the plan is on the calibration register (E01).

Key characteristics

Key characteristics are the few characteristics whose variation most affects fit, function or life. The customer may designate them on the drawing; you may add your own from the process risk review. For each, the plan records actual values from the first part on, the key characteristic register (D16) holds the data and the capability, and the control plan (E07) states the control and the reaction plan at the operation that produces it.

Method, frequency and record by class

ClassMethod we reach forStarting frequencyRecord
Key characteristicVariable gauge at the machine with a measurement study; CMM for positionsEvery part until capability is shownActual values
Critical item featureAs for a key characteristic, or as the customer specifiesEvery partActual values
MajorVariable gauge where the tolerance allows; attribute gauge otherwiseFirst and last piece, plus a frequency from the process's historyValues, or pass or fail for attributes
MinorStandard hand gaugesFirst and last pieceValues or pass or fail
Notes and process requirementsVisual against a standard; certificate review; receiving checks such as coating thicknessEvery part for visual notes; every lot for certificatesPass or fail; certificate number

Frequencies and the sampling basis

Initial frequencies are high on purpose: key characteristics every part until capability is shown, major characteristics first and last piece plus a frequency, notes every part at final. The plan header records the basis. AS9100D expects sampling used for acceptance to rest on recognized statistical principles and to suit the product's criticality; many aerospace customers also restrict sampling on their own terms, and their rules come first.

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.