The FAI and Production Readiness Kit HandbookChapter 4 of 22

Who does what

A launch needs an owner for the launch as well as owners for each piece of it. Agree this table with your plant manager before you start; in small shops one person often holds two roles, which is fine as long as the inspector and the package reviewer are not the same person.

RoleOwnsDoesDecides
Plant manager or program ownerThe launchChairs the readiness review; clears blocks; signs the decisionGo, Go with conditions, or No go
Quality engineerThe first article and the inspection planScreens triggers, balloons the drawing, plans inspection, reviews the packageFirst article scope; whether the package is ready to sign
Manufacturing engineerThe processRouting, programs, fixtures, tooling, process risk review, control planHow the part is made
PlannerThe traveler and the scheduleWrites the traveler; books machines and outside processesSequence and dates, with engineering
InspectorThe measurementsFirst pieces, the first article measurements, the CMM programs' first runsWhether a setup is released; pass or fail on each characteristic
Supplier quality engineerPurchased material and servicesApproves sources, flows requirements down, confirms customer approval of special process sourcesWhether a source can be used
Setup machinist and operatorsThe setup and the runSetup checks; make the first piece; follow the travelerWhen to stop and call for help
Quality managerThe systemRuns the weekly launch review, watches the measures, escalatesEscalation; who reviews packages

Who leads each stage

StageLeadsTakes partSigns
Order review and triggersQuality engineerProgram owner, plannerQuality engineer (scope)
Inspection planningQuality engineerManufacturing engineer, inspectorQuality manager (plan approval)
Process build and travelerManufacturing engineerPlanner, toolroom, programmerManufacturing engineer; quality (traveler release)
Readiness reviewPlant managerEveryone with a rated linePlant manager, operations, quality
First pieceSetup machinistInspectorInspector (release)
First articleInspectorQuality engineer, manufacturing engineer for any NCRInspector
Package review and submissionQuality engineer (not the inspector)Supplier quality for certificatesReviewer; approver

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.