Two reviews of the document that carries a job through the shop: one before the traveler is released to the floor, so it says what the drawing and the order require, and one when the job is complete, so the record shows every operation done, every part accounted for and every exception authorized.

  • Word
  • fillable PDF
  • Worked example
  • Your logo on it
  • Aegis Insights
Page 1 of the Production Traveler Review Checklist

Page 1 of the PDF. Every resource includes a fully worked example.

The problem it solves

The traveler (also called the router or the job card) is the one record that follows the part from the saw to the shipping dock, and it is where small gaps become escapes: an operation missing from the sequence, an inspection point that never made it from the inspection plan, a drawing revision that does not match the order, a quantity that drops from 60 to 58 with no NCR, a stamp in the wrong box, an operation done out of sequence with nobody's authorization. Auditors and customers read travelers closely because they show whether the process ran as planned. These two checklists catch the gaps twice: when the traveler is written and released, and when the job closes before the certificate of conformance is signed.

Who uses it

Planners and manufacturing engineers who write travelers; supervisors and quality engineers who release them; final inspectors and quality staff who close them before shipment.

When

Checklist 1 for every new or revised traveler before its first release to the floor, and for a sample of routine releases each month. Checklist 2 at the close of every job before the certificate of conformance is signed, or on a sample when your final inspection already closes each traveler.

Free to use, change and copy, in your own organization or with your clients; add your own logo, keep the Aegis credit. Part of: FAI and Production Readiness Kit. Clause references: 8.5.1, 8.5.2; also 7.5.3, 8.1.2, 8.5.6, 8.6, 8.7 (numbers only; use your own licensed copy of the standard).

Aegis Insights inside. Wherever this resource gives our own guidance, it is labeled Aegis Insights, so you always know what is our experience and what a standard or your customer requires.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard.

How to put it to work

Chapters of our free guides that use this tool.

  1. The kit and how the tools connectThe FAI and Production Readiness Kit Handbook, chapter 2
  2. The workflowThe FAI and Production Readiness Kit Handbook, chapter 3
  3. The traveler (E09)The FAI and Production Readiness Kit Handbook, chapter 8
  4. Setting it up in thirty daysThe FAI and Production Readiness Kit Handbook, chapter 17
  5. Quick referenceThe FAI and Production Readiness Kit Handbook, chapter 20

Related resources

  • Workbook

    Inspection Planning Worksheet

    Plan the inspection of every ballooned characteristic before the first part is made: where it is verified, by which method and gauge, how often, what gets recorded and what happens when it is out, with a check that every gauge can resolve its tolerance.

    Excel · PDFFree download
  • Checklist

    First-Piece Inspection Checklist

    Release every setup on evidence: nineteen setup checks, the first piece measured characteristic by characteristic with fail and near-limit flags, a suggested decision, and a shop-wide log that shows which setups keep needing a second try.

    Excel · PDFFree download
  • Checklist

    First Article Inspection Planning Checklist

    Decide whether a job needs a first article and how much of one, then plan it before the part is made: requirements, the production process, the ballooned characteristics, gauges, materials, special processes, people and records, with a shop-wide log from trigger to customer approval.

    Excel · PDFFree download
  • Checklist

    Production Readiness Review Checklist

    Decide, on evidence, whether a new or changed part is ready to make product: thirty-eight readiness checks across thirteen areas, a record of the decision and its conditions, and a summary that shows what is blocking the launch.

    Excel · PDFFree download
  • Workbook

    Key Characteristics Monitoring Register

    Every key characteristic with its limits, control method and reaction plan; every measured value; and capability worked out from the values, so you know which KCs are capable, which are not, and which have too little data to say.

    Excel · PDFFree download
  • Template

    Control Plan Template

    A control plan in the columns aerospace customers expect, with a line check that flags missing reaction plans, methods, gauge studies and capability on key characteristics before a reviewer does.

    Excel · PDFFree download

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

These tools help you run the work by hand. When you want the whole picture of your quality system from the records you already keep, that's what the AeroAssure Audit Defense Pack and the IA9100 Transition Gap Analysis do.