The FAI and Production Readiness Kit HandbookChapter 15 of 22

The weekly and monthly rhythm

RhythmWhoWhatTool
DailyInspectors, setup machinistsFirst pieces released on evidence; first-piece log keptE12
Weekly, 30 minutesQuality manager, quality and manufacturing engineers, planningThe launch review: the FAI plan log (late, review due, waiting for the customer); planning checks overdue; readiness conditions due; triggers raised by changes this weekD07, D09, D08
WeeklyMaintenance, toolroomOverdue equipment and tooling; items in service but not validated; product impact assessments openE10
MonthlyQuality manager and plant managerMeasures (chapter 16); first-time release rate by machine and part; rejected packages and their causes; key characteristic capabilityD07, E12, D16
QuarterlyTop managementLaunch performance as a management review input; parts approaching a long lapse; resources for upcoming launchesD07 summary

The weekly launch review has a fixed agenda: first articles late or waiting; packages due for review; readiness conditions due this week; triggers from this week's changes; one decision for anything stuck. Thirty minutes, standing if you can.

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.