On August 7, 2026, the second-shift setup technician at Meridian Aerostructures left. Twelve days later, a setup on second shift ran 8 brackets with a superseded program. This is how the kit carried the situation from the failure to a covered shift, using the record numbers in the tools' own worked examples.
Worked example
The failure and the retraining gate (G03)
August 19. K. Walsh, level 2 on 3-axis setup, setting up alone, loads program O5120 rev C instead of rev D. The first-piece CMM program, chosen the same way, passes the part. NCR-26-298; the same error as NCR-26-154 in April on first shift, whose corrective action (CAPA-26-026) had closed with 'operator retrained'. CAPA-26-026 reopens as an 8D.
August 20 to 24. The gate (RT-26-007). The nine questions show a level 4 setter made the same error in April; the setup sheet had no revision step; the machine folder held three revisions with near-identical names; second shift had nobody qualified to ask. Classification: method or instruction problem, with a skill gap and a staffing gap contributing. Retraining appropriate: partly, and only alongside changes to the job.
August 24 to September 11. The job changes. No setup alone below level 3 (L. Nguyen, August 24); superseded programs archived where machines cannot load them (J. Alvarez, August 28); traveler prints program revisions and the setup sheet adds a signed revision match (M. Okafor, September 4); CMM programs released against the drawing revision (September 11).
Worked example
The matrix and the training plan (G01)
The new step becomes a skill. S07, setup revision check, goes on the Skills tab with a minimum of six. All seven setters on both shifts are trained by S. Haddad, September 8 to 18.
Coverage on October 31. Second shift: six people, one 3-axis setter (F. Osei), nobody who can set up Mill 7, release a first piece or stamp final inspection. Plant-wide: four skills held by one person (lathe setup, CMM programming, skin-panel countersinking, the certificate at the shipping desk); final inspection one short of its minimum.
The plan. K. Walsh to level 3 on 3-axis setup by November 30; F. Osei on first-piece release; D. Ruiz on CMM programming (management review action MRA-26-08); G. Park on certificates; N. Petrov on lathe setup (two months overdue: on the agenda); a contract inspector on second shift from November 2 (MRA-26-11) until the hire (MRA-26-03).
Worked example
Authorization (G02), evaluation (G04) and awareness (G05)
October 28. Qualification QR-26-014. F. Osei qualified for first-piece release on Mills 4 and 6: five first pieces inspected alongside D. Ruiz, all 142 characteristics agreed, test 92 percent, evaluated by M. Okafor (not the trainer), vision exam October 6. Qualified with limits; stamp M-21 issued and logged. Second shift can now release its own setups.
The registers on October 31 show what else needs a decision: D. Ruiz's vision exam overdue since October 15; K. Ito's certificate authorization expired in August; E. Moreno's first-piece authority lapsed after six months unused; R. Chen's stamp due for requalification on November 4. The stamp of the setup technician who left (M-18) was recovered and logged on August 7.
October 27. Evaluation TE-26-006. The revision-check training evaluated on the job: 21 of 21 observed setups with the step signed; no mismatch reached a part in 124 setups; the step caught 4 mismatches before cutting. Effective so far; the corrective action's 90-day check continues. C. Lindqvist, hired in September, reached level 2 and is retrained (TE-26-012, not effective).
September 22. Briefing. A week after the short-thread escape at Customer A (example), F. Osei and R. Chen briefed second shift at Mill 6 with a sectioned fitting and both gauges: where the part goes, what happened, what changed, stop, tag, tell. On October 26 three people asked at their machines could answer all three questions (TE-26-007).
Worked example
Management review: the resources input
At the Q3 management review on October 22, the coverage view and the authorization register were the evidence behind the resources input: four open positions including the second-shift inspector, Mill 7 overtime at 11 percent of hours, second shift carrying a third of the people and almost none of the authorizations. The outputs were the contract inspector (MRA-26-11), a weekend cell for Mill 7 (MRA-26-12) and the risk register entry for loss of second-shift setup capability (MRA-26-13).
Aegis Insights
What the example shows
The kit did not prevent the setup technician leaving. It turned his departure into a visible coverage gap, refused 'retrained' as the answer to the failure that followed, changed the job so the error could not recur on any shift, qualified a second-shift lead on evidence, showed the training worked, and gave the general manager the facts for the resource decisions.
← Chapter 22 For your general manager: one page Chapter 24 → Quick reference for supervisors: one page
Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call . We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.
A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.
Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.
Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.