Worked example: one change through the whole kit

Meridian Aerostructures machines bracket 5120-100 for Customer A (example). On September 29, 2026 the customer released drawing rev D. This is how the change moved through every tool in the kit, with the record numbers you will find in each tool's own worked example.

DateEventTool and record
Sep 29Customer A releases drawing 5120-100 rev DCN-8812
Oct 1Change logged; assessment startsD11: ECN-26-071
Oct 7Change board approves; process change openedD11; E13: PC-26-019
Oct 8Customer approves rework of rev C stockC-2238
Oct 9Process change approved, criterion setE13
Oct 12 to 14Process change notice sent and acknowledgedPCN-26-07
Oct 13Trial: five of five in toleranceE13
Oct 15 to 16Documents and program issued; rev 6 deleted from both controlsA13: IS-26-140 to 143
Oct 19First rev D lot L-2702 releasedD11, E13
Oct 22Partial FAI; configuration updatedFAI-26-071; D10: CSA-26-118
Oct 23Configuration and point-of-use checks: matchD10: CC-26-033; A13: PU-26-066, 067
Oct 28Customer accepts the FAIFAI-26-071
Oct 30ECN closedD11
Nov 2Process change closed after three clean lotsE13

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.