Customer and engineering changes

How changes arrive

Customer changes reach a supplier in more ways than most change procedures admit. List yours, and make each one feed the same log:

  • A new drawing or model revision, released on a portal or sent by email.
  • A change notice that describes the change before the drawing is released.
  • A purchase order amendment that calls a new revision, quantity or delivery (8.2.4).
  • A revised specification: material, finish, process, test or packaging.
  • Revised quality clauses or supplier requirements, which can change what you must do on every order.
  • A deviation or waiver the customer grants for a limited quantity.

Our own engineering changes join the same log: a change to a router or a fixture we designed, a corrective action that changes the product's documents, an obsolete material replaced from the customer's approved list.

The impact assessment

Every product change goes through the twenty-line impact screen on the Engineering Change Impact Assessment (D11). Each line is answered Affected, Not affected or Not sure. For every Affected line, the actions go on the Change actions tab with an owner, a due date and, when done, the evidence. The lines most often skipped are in the middle: programs, inspection plans, setup sheets and gauges. They live in different places, belong to different people, and none of them is the drawing.

Three decisions on every assessment cause most of the trouble later, so D11 makes each a field:

  • Product safety. Can the change affect a safety-related characteristic, or the part's behavior in service? Answered before approval, with the reason (8.1.3; the IA9100 screen, D02, if you are preparing for the transition).
  • First article inspection. A design change normally calls for at least a partial FAI on the characteristics it touches (AS9102); some customers ask for more. Plan it at approval, not after the first lot.
  • The customer question. Does anything about how we implement this need the customer's approval or notice: a disposition of old-revision product, a process change their clauses list, a deviation?

Classifying changes: examples

Use your customer's classes where the contract gives them. Where it does not, these examples show how we classify common changes and what each usually needs. Every row is still a decision for your change board, checked against AS9102 and the customer's clauses.

ChangeClassFAICustomerUsual traps
Hole size or position changed on the drawingMajorPartial on the changed featuresImplement their changeProgram in machine memory; CMM program not revised
Tolerance opened, nothing elseMinorUsually partial on that featureImplementOld inspection plan still rejects good parts
Characteristic marked as a key characteristicMajorPartialImplement; often a capability requirementControl plan and KC register not updated
Material or finish specification revisedMinor or major, by contentDepends on what changedImplement; flow downSupplier certificates on the old revision
Note or title block correctionAdministrativeNone, reason recordedImplementTreated as nothing, so the revision is never issued
Order amendment: new revision from a given lineAs the drawing changeAs the drawing changeContract reviewLots straddling the effectivity line
Packaging or marking changeMinorNone, reason recordedImplementOld labels in the packing area
Our router: operations resequencedProcess changeCheck AS9102 and clausesNotice if the clauses askLogged as a document change only (use E13)
Customer deviation for a limited quantityTemporaryNone for the deviation itselfTheir written approvalDeviation applied beyond its quantity or dates

Effectivity and the old revision

Agree one effectivity point with the customer: a lot, a serial number, an order line or a date. Every lot before it stays at the old revision; every lot from it is at the new one. Then decide, lot by lot, what happens to product at the old revision: work in process, finished stock, material and parts at suppliers, and product already delivered.

Product at the old revisionOptionsWatch for
Work in processComplete to the old revision if it falls inside the old effectivity; otherwise rework to the new revision, or scrapA lot finished to the old revision after the effectivity point is nonconforming
Finished stockShip against old-revision order lines; rework to the new revision under a written instruction (with customer approval where needed); scrapRe-identification: marking, traveler and certificate must show the new revision
At suppliersRevise the purchase order; let the supplier finish to the old revision only where it is still usableSupplier certificates calling the old specification revision
DeliveredUsually not affected; tell the customer where the change bears on what they holdRetrofit or return needs the customer's agreement

Approval, implementation and closure

The change board approves the assessment before anything moves. Implementation starts at the effectivity point, with the FAI on the first product. A change is closed only when every action is done with its evidence, the FAI is accepted where needed, the customer's approval is on file where needed, the old revision is gone from every point of use, and the configuration register is updated. D11's closure section checks each of these and will not read Yes until they are true.

Before you close a change

  • Every impact line answered; none left Not sure8.5.6
  • Approved by the change board before any product was made to the change8.5.6
  • Product-safety question answered before approval, with the reason8.1.3
  • Every action done, with evidence an auditor could pull8.5.6
  • One effectivity point agreed; every old-revision lot dispositioned8.5.2
  • Customer approval or notice on file where the contract needs it8.2.4
  • Changes flowed down on purchase orders and to outside processors8.4.3
  • New programs proved and validated before use8.5.1.1
  • FAI done and accepted where needed (AS9102)8.5.1.3
  • Old revisions withdrawn from every point of use, machine memory included, and signed for7.5.3
  • Configuration register and status accounting updated, with the effectivity8.1.2
  • A configuration check made on the first lot at the new revision8.1.2

Answer each: Yes / No / N/A, with your notes and evidence. The Word and fillable PDF handbook have the check boxes.

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.