Electronic control of programs and documents

Most old revisions that reach a machine travel electronically: a program in control memory, a file on a USB stick, a drawing saved to a desktop. Paper control alone cannot stop them. The arrangement below costs little in a small shop and closes most of the paths.

ElementHow we set it upWhy
One released folderA single network folder per part for released programs, setup sheets and inspection plans, read-only for everyone except document control and the programmer releasing a changeOne place to look; nobody edits a released file by accident
Work in progress kept apartPrograms being written or proved live in a separate folder that the machines cannot load fromAn unproved program cannot be run by mistake
Revision in the name and the headerFile name and program header both carry the revision, and the header shows on the control's screenThe operator and the auditor can read it at the machine
Superseded folderOld revisions move to a superseded folder, read-only, kept for traceabilityHistory without risk
Machine memoryPrograms are loaded from the network for each job; anything left in memory is cleared at every program issue and checked at configuration checksMemory is where old revisions hide
Removable mediaNo USB sticks at the machines, or only numbered ones held by the supervisorA stick is a binder nobody audits
CMM programsThe same rules as CNC programs: one released folder, revision in the header, proved before releaseThe CMM decides what is accepted
Customer models and drawingsDownloaded once from the customer's portal by document control into the controlled drawing folder; nobody works from email attachmentsOne copy, one revision
BackupsNightly, with a restore tested twice a yearA record you cannot restore is a record you do not have

Where the shop uses a DNC system or a production data system, the same rules apply inside it: released and work-in-progress areas kept apart, revision visible at the machine, and old revisions removed from the machine side at every change.

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.