IA9100 draft: based on the IAQG's published changes. IA9100 is not yet final, and the final text may change these topics and clause numbers.

Every tool in the package follows the same few principles. They come from watching transitions go well and badly in small aerospace shops, and they are the reason the tools are built the way they are.

  1. Answer from the record, not from memory. Every self-check answer names the record looked at. A plan built on what people believe is in place fails at the first sample.
  2. Records first, procedures second, training third. The record is what the auditor samples and what shows the change working. Procedures written around a working record are short and true; training on an issued procedure sticks.
  3. Do the cheap things now. About a third of the change items are small and useful for today's AS9100D audits: a tested restore, a safety line on the change form, counterfeit training for the buyer, a sentence in the PO terms. Do them before the final text.
  4. Hold the wording, not the work. Where the draft may still change, put the practical record in place and hold the procedure and manual wording. Rewriting a quality manual twice costs more than it teaches.
  5. Plan in windows counted from the final text. No one can date the transition yet. Invented dates cost the plan its credibility the first time one moves.
  6. One owner and one record per line. Each change item has a named owner and a named record that will show it done, written before the work starts.
  7. Review it where the work is decided. The transition is reviewed in the monthly production or operations meeting, not in its own meeting, because it competes with deliveries for the same people.
  8. Counts, not scores. Management sees plain counts of your own answers and a plain share of applicable items shown. No weights, no readiness rating to argue about.

Need more than one resource, or not sure where to start? Book a complimentary 30-minute Aegis Quality Guidance Call. We'll find the tools that fit your situation and a sensible place to start. No sales pressure, no obligation.

IA9100 draft: based on the IAQG's published changes. IA9100 is not yet final, and the final text may change these topics and clause numbers.

A management aid, not certification or a registrar audit. Using it does not by itself show conformity to AS9100D or any other standard, and your customers' requirements may add to it.

Clause numbers refer to AS9100D (SAE AS9100 Rev D) unless another document is named. The standards' text is not reproduced here: use your own licensed copy.

Aegis Insights are our own guidance, labeled wherever they appear: how we approach this work, not a requirement of any standard or customer.